Gill Parkway

Gill Pkwy

Description

Extension of Perry Avenue from FM 1409 to FM 565. The scope of work also includes the construction of reinforced concrete pavement, sidewalks, storm sewer, water line, sanitary sewer, replacement of FM 565 culvert crossing, signing & striping, and traffic control.

Contract Amount

$8,934,309

Contractor

Angel Brothers

Project Award Date

February 24, 2020

Estimated Project Completion Date

May 1, 2021

Status

Complete

Project Map (Click to enlarge)

Gill Parkway Location Map